Chandigarh University has decided to conduct an entrance cum scholarship test named as Chandigarh University Common Entrance Test (CUCET) for admission to various programs so as to provide an opportunity to bright and inquisitive young minds from across the country to study in most challenging and diverse academic environment.
CUET Sample Papers Aspirants who wish to take the CUET 2023 exam can practise the CUET 2023 sample papers to understand the exam format. Candidates will get a better understanding of the CUET syllabus and exam pattern through the CUET 2023 sample papers. The CUET sample papers contain MCQs based on cases, assertions, reasons, statements, and arguments/conclusions, and they cover various domains.
CUCET ME-EE Sample Paper
1. A synchronous machine has higher capacity for
- leading p.f.
- lagging p.f.
- it does not depend upon the p.f. of the machine
- voltage
2. The positive, negative and zero sequence impedances of a solidly grounded system under steady stale condition always follow the relations
- Z0 < Z1 < Z2
- Z1 < Z2 < Z0
- Z1 > Z2 > Z0
- Z1 = Z2 = Z0
3. When a fault occurs on the system a circuit breaker
- opens automatically
- closes automatically
- opens manually
- closes manually
4. If the length of the arc of circuit breaker increases. its resistance
- decreases
- be extinguished
- remains same
- increases
5. If the dielectric strength of the medium between contacts builds up more rapidly than the restriking voltage, then the arc will
- decrease
- not be extinguished
- increase
- be extinguished
6. The relay with inverse time charac·eristic will operate within
- 5 sec
- 5 to 10 sec
- 10 to 15 sec
- 30 sec
7. The critical clearing time is related to
- steady state stability limit
- transient stability limit
- short-circuit current limit
- insulation limit
8. If the voltage at the two ends of a line are 132 kV and its reactance is 40 ohm, the capacity of the line is
- 435.6MW
- 217.8 MW
- 251.5MW
- 500MW
9. The function of Lightning arrester is
- To limiting the short-circuit fault current
- To provide path to high voltage surge to earth
- To stop arcing
- To reduce arcing
10. Distance relays operation is dependent upon .
- ratio of current to current
- ratio of voltage to current
- ratio of voltage to voltage
- ratio of power to voltage